How to get a Tiny Home

Thinking about a backyard pod house or tiny home? Our prefab pods arrive fully built, with walls, kitchen, bathroom, double-glazed windows and wiring all done. Here's what happens between placing your order and stepping inside your new backyard space, and how long each stage takes.

Typical total time: 20–24 weeks from order confirmation to delivery in the Perth metro area.

1

Week 0 · Before you order

Site check & approvals

Most of our customers set the Savanna Pod up on a registered trailer (sold separately), which means it's treated as a tiny home on wheels rather than a building. There's no building permit or engineering certification involved. You apply to your local council for a temporary accommodation approval, which can be granted for up to two years at a time and renewed.

Our pods are not certified to the National Construction Code (NCC), so they aren't suited to being fixed permanently to the ground as a dwelling without further works and certification. Any approvals for your site are your responsibility as the owner, so we suggest a quick chat with your council before ordering. We can provide the specs, photos and test reports they'll ask for.

We'll also confirm access for delivery: gate width, overhead lines and where your pod will sit.

You'll need: your address, a rough idea of placement, and photos of the access route.

2

Week 1 · Order confirmed

Deposit & order lock-in

Once you're happy, a 20% deposit secures your pod and your place in the production schedule. You'll receive a written order confirmation with your specifications, inclusions and estimated delivery window.

3

Weeks 1–2 · Make it yours

Choose your interior finishes

You select your wall panels, kitchen cabinetry and flooring from our curated ranges, and we send you a rendered preview of your exact colour combination before anything goes into production.

Included as standard: double-glazed windows with fly screens, silica-free stone benchtop, full kitchen and bathroom fit-out.

4

Weeks 2–9 · In production

Your pod is built

Your pod is built to your specification in a dedicated modular housing facility, with steel frame, insulated sandwich panel walls, wiring, plumbing and finishes all completed under one roof in around 45 days. The electrical fit-out is to Australian standards (AS/NZS) with Australian outlets, plumbing fixtures and fittings are WaterMark certified and WELS rated, and materials are tested asbestos-free by a NATA-accredited Australian laboratory.

We share progress photos during the build so you can watch your pod take shape.

5

Weeks 9–21 · On the water

Shipping & customs clearance

Your finished pod is loaded into a shipping container and sails to Fremantle over 10–12 weeks. We manage the import: freight, insurance, biosecurity and customs documentation, including the independent lab reports Australian Border Force expects for modular buildings.

6

Weeks 21–24 · Delivery

Into position and connected

Your pod arrives fully assembled. We'll help coordinate placement to suit your site, through our transport and crane contacts or a contractor of your choice. Once it's in position, a licensed electrician connects the pod's single inbound power supply and a licensed plumber connects water and drainage.

Hot water pipework comes pre-installed; your plumber fits a locally sourced hot water unit during connection.

Pod house timeline at a glance

Stage Typical duration
Site check & approvals Before ordering
Order confirmation & finish selection 1–2 weeks
Production About 6–7 weeks
Shipping & customs (to Fremantle) 10–12 weeks
Delivery & connection 1–2 weeks
Total: order to move-in ready 20–24 weeks

Why a pod instead of building on site?

A granny flat or backyard studio built on site in Perth can take the better part of a year with trades, weather delays and approvals. A prefab pod arrives as a complete, finished tiny home with kitchen, bathroom, insulation and electrics done. On a registered trailer, the approval is a simple temporary accommodation application to your council rather than a full building permit, making it one of the fastest ways to add a guest space, studio or home office to your backyard.

Ready to start the clock?

Your backyard. Your way. Order this month and your pod could be in place within six months.

View the Tiny Homes